Approval was given to the Harrison Square Walkway proposal today at the Redevelopment Commission and Local Historic Preservation Board’s meetings.  The walkway will enter the building as shown here:

Highlights:

  • The Goldstine Foundation will give $550,000 for costs of the project.

  • Due to additions to the project, the cost will be $1,831,394 instead of the first reported $1 million.  This is because of an added elevator, elevator shaft,  stairwells and reconfiguration of a storage area on the third floor. 

  • The walkway will not physically connect into the Indiana Hotel, instead, expansion joints will complete the connection.

  • The project will be completed by the time the new Courtyard by Marriott Hotel opens.

For more details, read my notes from the meetings.